DemoRiverside is invented. Every figure on screen is computed by the real engines from fixture data, so the numbers are honest about the fixtures and the fixtures are not real.
Capo
Riverside rolloutGated Scrum with an ADKAR overlay
DE
As of period 2

Performance

Measured against baseline version 1.

2026-05-01
As it stood atDiscovery gate2026-04-16
LaunchDiscovery gatePeriod 2 closeDesign gatePeriod 3 closePeriod 4 closePeriod 5 closeWhere it stands now

An approval point that was passed. Earned value is recomputed through that close, against the baseline that was in force at the time, and actual cost is never restated. The plan, the register and the people show today, because Capo keeps no history of those yet and will not pretend otherwise.

Ensemble Index
71
Good: Holding
This plan is broadly holding, with something worth watching.
Tuning
60
Watch: Under strain
Treat these numbers as indicative. The weakest link is freshness.
Cost performance
0.9
CPI
Watch: Under strain
15k over the value earned.
Schedule over time
0.65
SPI(t)
Off: Not holding
About 14 working days behind.
How to read this
Ensemble Index
One score from 0 to 100 for how much this plan deserves to be believed, combining delivery performance, plan integrity, stakeholder alignment and team development. 85 and above is holding, 70 to 84 is holding with something to watch, 50 to 69 is under strain, below 50 is not holding. Arithmetic, never written by a model.
Tuning
How much the Ensemble Index itself deserves to be believed, from 0 to 100, based on how objective, how fresh and how confirmed the underlying measurements are. A low Tuning never quietly discounts the Index. Both are shown so a confident number resting on thin evidence is visible as exactly that.
Cost performanceCPI
The value of work finished divided by what was spent to finish it. 1.00 is a dollar of work for every dollar spent. Below 1.00 the work is costing more than it was budgeted to cost, above 1.00 it is costing less.
Schedule over timeSPI(t)
How much calendar the project has earned against the calendar it has used. 1.00 is on the baseline. 0.90 is roughly one working day lost in every ten. The reading underneath converts it into working days ahead or behind.
Good, watch, off
Each headline figure carries a state, drawn as a shape with its word so it reads without colour. Good, a circle with a check, is holding: a score of 70 and up, or a performance index of 0.94 and up. Watch, a diamond with a dash, is under strain: 50 to 69, or 0.81 to 0.93. Off, a square with a cross, is not holding: below 50, or below 0.81. A blank figure never takes a state.
A blank where a number should be
A figure that cannot honestly be computed is left blank with the reason printed beside it. It is never shown as zero and never filled in with a guess.
Cumulative performance
Planned, earned and actual
The three lines
PlannedPV
What the baseline said would be finished by this date, in money. Drawn as a dashed line.
EarnedEV
The budgeted value of what is actually finished. Earned below planned is work running late, earned below actual is work running expensive.
Actual costAC
What has really been spent to date. It is never restated after a period closes.
Forecast at completion
999k

Against a budget of 900k.

If this rate holds
999k
If it was a one off
915k
If both persist
1.34m
Bottom up
Not available

Variance at completion is -99k. To finish on budget, the remaining work would have to run at a cost performance of 1.02.

The four scenarios
Forecast at completionEAC
What the whole project is now expected to cost. Four scenarios are listed rather than one number, because the honest answer is a range: if the current rate holds, if the overrun was a one off, if cost and schedule problems both persist, and what the team estimates from the bottom up.
Budget at completionBAC
The approved budget for all of the work in the current baseline.
Variance at completionVAC
Budget minus forecast. A positive figure is money expected to be left over, a negative figure is the expected overrun.
To complete performanceTCPI
The cost performance the remaining work would have to run at to still finish on budget. Well above 1.00 means the plan is asking for a rate this project has not yet achieved.
Tuning
What these numbers rest on
  • Objective measurement60

    40 percent of the budget is measured by somebody's judgment of percent complete rather than by a countable fact.

  • Schedule signal79

    16 percent of the budget is level of effort, which earns planned value by definition and therefore cannot show a schedule variance.

  • Freshness0

    The newest progress measurement is 107 working days old.

  • Measurement coverage31

    69 percent of the budget sits in work packages nobody measured this period.

  • Cost agreement100

    The actual-cost sources agree, so no policy tie-break was needed.

  • Human confirmation85

    3 of 24 items were filled in by the planning engine and never confirmed by a person.

  • Index coverage100

    Every dimension of the Ensemble Index could be computed.

How to read these factors
Each factor scores 0 to 100
Higher means the measurement underneath is more trustworthy. A factor below 60 is printed in rust, and the sentence beside it says what would raise it.
Tuning
How much the Ensemble Index itself deserves to be believed, from 0 to 100, based on how objective, how fresh and how confirmed the underlying measurements are. A low Tuning never quietly discounts the Index. Both are shown so a confident number resting on thin evidence is visible as exactly that.
Level of effort
16 percent of budget cannot show a schedule variance

Level of effort earns planned value by definition, so schedule performance is diluted by exactly this much. These are the packages measured that way.

Why this matters
Level of effort
Work that earns its planned value simply by time passing, such as management or support. It can never show a schedule variance, so the share of budget measured that way is stated openly rather than left to dilute the number quietly.
Schedule over timeSPI(t)
How much calendar the project has earned against the calendar it has used. 1.00 is on the baseline. 0.90 is roughly one working day lost in every ten. The reading underneath converts it into working days ahead or behind.